SAUGUS — Construction is finally underway at the historic Belden Bly Bridge.
Earlier this week, a press release from the Massachusetts Department of Transportation (MassDOT) stated that following some initial water-related utility work, transit construction company SPS New England will demolish remaining approach spans and substructure elements associated with the 109-year-old bridge to make room for a new, permanent structure.
Formerly known as the Fox Hill Drawbridge, the new bridge, which spans the Saugus River to connect Lynn and Saugus at Western Ave. and Route 107, will be located on the same alignment as the original, immediately west of the existing temporary drawbridge constructed in 2013 as a means to allow one lane of traffic to run in each direction.
According to representatives for MassDOT, the overall project will consist of the construction of a new bascule moveable bridge and new approach bridge spans, as well as the reconstruction of roadway approaches.
Significant modifications and upgrades, including sidewalks and a bicycle lane, will also be constructed at the intersection of Route 107 and Ballard Street on the Saugus side.
The news has been a long time coming. Construction on the bridge was originally slated to begin in Spring 2019, but was later delayed to this year.
“That may have been an initial project schedule, however, as always, the schedule of work is dependent upon numerous factors, including design work and considerations,” MassDOT spokesman Patrick Marvin told The Item in July 2019.
The existing temporary bascule movable bridge will remain operational until the new bascule moveable bridge is constructed and fully operational. During the majority of the project’s construction, a minimum of two vehicular travel lanes and one sidewalk will be maintained along Route 107.
“MassDOT will continue to coordinate construction activities in a manner that minimizes impacts to marine traffic in the area of the project,” the department’s press release read.
Field work associated with the $99.3 millsion project is projected to be completed in March 2026. Work hours for the demolition activities, which are expected to run through February, will be 7 a.m. to 11 p.m., Monday through Saturday.
MassDOT has warned that those traveling through the area should expect delays, reduce speed, and use caution.